Kitchen remodel: full gut with gas, sewer and water lines relocated

Kitchen remodel: full gut with gas, sewer and water lines relocated

A full-gut kitchen remodel in Dana Point for a homeowner who knew exactly what she wanted. We worked with her designer to get the finishes she was after, and the gas, sewer and water lines were completely relocated as part of the job. The finished room has two-tone cabinets, with painted uppers to the ceiling over light wood lowers and slim brass pulls, plus a ribbed wood island with a veined stone-look top. A freestanding griddle range sits under a painted hood, with a pot filler on the range wall. The high-end finishes she chose made the job take a little longer, 9 weeks in all. CRS's owner says she was extremely happy with the result and that seeing it made the extra time worth it.

Project photos

Project details

What made this Dana Point kitchen remodel high-end?

The finishes. The homeowner knew exactly what she wanted and worked out the selections with her designer, and CRS worked with the designer to get those finishes into the kitchen. The finished room has two-tone cabinets with painted uppers to the ceiling, light wood lowers and slim brass pulls. There is a ribbed wood island with a veined stone-look top, and a freestanding range with a flat griddle under a plain painted hood. The countertop material runs up the wall behind the range, where a pot filler is mounted.

What work happened behind the walls?

This Dana Point kitchen was a full gut, and the gas, sewer and water lines were completely relocated. That gas and plumbing work is done after demolition and before the new cabinets and countertops go in.

How long did the Dana Point kitchen take?

Nine weeks. The high-end finishes the homeowner chose made the job take a little longer, and CRS's owner says the results were worth the extra time.

Did CRS work with the homeowner's designer?

Yes. The homeowner on this Dana Point kitchen had her own designer and knew exactly what she wanted. CRS worked with the designer to get the finishes she was after and built the kitchen to her selections.